Modular groundworks solutions from Mabey Hire have been used on a renovation project at 120 Fleet Street in London.

Enabling and demolition specialist Erith is delivering the enabling works on the refurbishment of the Grade II listed Daily Express building and redevelopment of the River Court commercial building.

Development manager CO-RE is detaching the Daily Express building from River Court, which will be replaced with a new tower. Others involved in the project are Bjarke Ingels Group as architect, Lendlease as main contractor and AKT II as structural engineer.

Creating a new 52,000m2 development, River Court – renamed  Evergo Tower – will step up from seven storeys to 21 at its uppermost point and will form a new sustainable commercial workplace in the heart of the city. 

As part of Erith’s appointment, the original River Court superstructure had to be demolished from the top down to ground floor level. It was for this section of the project that Erith turned to temporary works specialist Mabey Hire for support.

Erith project manager Steven Gillam explained:

“We were contracted to perform a number of works for this project, which included completing any residual soft stripping work, erecting perimeter scaffolding, and the construction and installation of a tower crane and base.

“We were also contracted to demolish the original River Court superstructure to clear space for the new office tower. It was during this section of the scheme that, due to its complexity, extra support structures were required to ensure the stability of the ground to enable us to carry out the substructure demolition works safely; and this is where we turned to Mabey Hire.”

A key challenge was site access in a constrained setting.

Gillam said:

“Due to the confined city centre location, we were unable to bring in a larger tower crane, meaning we were limited to a 10t capacity crane. This was a key factor that we had to consider when looking for temporary groundworks support, and Mabey Hire was able to meet the challenge head on.”

The temporary works scheme supplied by Mabey Hire incorporated its Super Bracing Strut-1000 and a Mass 25 propping tower.

Mabey Hire major projects sales manager Arran Philippou said: “Our Super Bracing Strut was the perfect fit for this project due to its modular construction, meaning it could be split into two sections and easily transported to site. Individually, each section was within the weight limit of the onsite tower crane, enabling it to be safely lifted into position and assembled on site.

“We also designed, supplied and pre-assembled a temporary support tower, constructed from our Mass 25 props. Due to the ground level being seven metres below the strut installation level, this propping tower provided intermediate support during both the installation and dismantling of the Super Bracing Strut, further ensuring the safety of those on site.”

Another key project constraint was time, with Gillam emphasising that it was necessary to have equipment fitted quickly to allow continuation of main works.

“Mabey Hire really helped with this aspect, with its technical, engineering and delivery departments being extremely supportive throughout the whole operation, delivering the equipment seamlessly to site,” he said.

“What’s more, Mabey Hire was able to deliver the propping tower preassembled, which really sped up the installation and dismantling of the systems and provided a significant programme saving overall. From our initial enquiry to the kit arriving on site took under four weeks, which was extremely beneficial for us.”

As part of the wider scheme, some existing foundations and basement structures, which remain from the former River Court building, will be reused within the new design. Additional foundations will be added progressively, towards the site’s rear, to support the increased massing. AKT II said this can save around 35% of embodied carbon within the below-ground construction.

Developer Chinese Estates Holdings’ Evergo Tower is expected to open in the first half of 2026.

 

Source: Ground Engineering

 

Membranes & Envelope Solutions by Rothoblaas: Revolutionizing Construction with Efficiency & Sustainability

In the fast-paced world of construction, the demand for innovative solutions that prioritize energy efficiency, sustainability, and faster installation is growing. Recognizing this need, Rothoblaas, a leading provider of construction products and solutions, has developed a range of cutting-edge membranes and envelope solutions that are revolutionizing the industry. With a focus on off-site application and longer protection of timber, Rothoblaas is reshaping the way buildings are constructed while ensuring optimal energy efficiency.

Energy Efficiency: A Top Priority
In today’s world, energy efficiency is a crucial aspect of sustainable construction. Rothoblaas understands this necessity and offers an extensive range of membranes and envelope solutions designed to enhance the energy performance of buildings. By providing effective thermal insulation, these solutions significantly reduce heat loss or gain, leading to reduced energy consumption and lower environmental impact. As the world grapples with the challenges of climate change, investing in energy-efficient construction materials and techniques is not just a wise decision, but also a responsibility.

Off-Site Application: A Game-Changer
One of the standout features of Rothoblaas’ membranes and envelope solutions is their ability to be applied off-site, ensuring faster and more efficient installation on-site. This innovative approach brings numerous benefits to construction projects. Firstly, by applying membranes in a controlled environment, the quality of the installation is greatly improved, minimizing errors and reducing the risk of water penetration or air leakage. Secondly, the off-site application allows for precise and accurate measurements, resulting in a seamless fit and enhanced performance. This process also reduces the time required for on-site construction, leading to significant cost savings.

 

Longer Protection of Timber: Preserving Durability
Timber is a popular and sustainable material in modern construction due to its low carbon footprint and aesthetic appeal. However, it requires careful protection to ensure its durability and longevity. Rothoblaas’ membranes and envelope solutions are designed with timber preservation in mind. These advanced materials act as a protective barrier, shielding the timber from moisture, UV radiation, and other damaging elements. By employing these solutions, builders can extend the lifespan of timber structures, reducing the need for frequent maintenance and replacement. This not only saves costs but also contributes to a more sustainable and resource-efficient approach to construction.
Versatility for Various Construction Types and Systems
Rothoblaas understands that construction projects come in various types and sizes, and each requires tailored solutions. Their range of membranes and envelope solutions cater to a wide array of construction types and systems, making them versatile and adaptable to diverse project requirements. Whether it’s a residential building, a commercial structure, or an industrial facility, Rothoblaas offers solutions that meet the specific demands of each application. This flexibility allows architects and builders to confidently integrate these products into their designs, knowing they will deliver superior performance and reliability.

Rothoblaas as the solution provider
Rothoblaas’ membranes and envelope solutions have emerged as game-changers in the construction industry, revolutionizing the way buildings are designed and constructed. Through their emphasis on energy efficiency, off-site application, and longer protection of timber, these innovative solutions offer a sustainable and efficient approach to construction. With their versatility and adaptability, Rothoblaas’ products can be seamlessly integrated into various construction types and systems. By embracing these advanced solutions, builders can not only meet the demands of energy efficiency and sustainability but also achieve faster installation, reduced maintenance costs, and enhanced durability. It is time for the construction industry to embrace the future of building construction with Rothoblaas’ membranes and envelope solutions and take a step towards a more energy-efficient and sustainable future.

Embrace Energy Efficiency Today
As the world faces increasing energy challenges, it is imperative for the construction industry to prioritize sustainable and energy-efficient practices. Rothoblaas’ membranes and envelope solutions offer a clear pathway towards achieving this goal. By integrating these cutting-edge materials into construction projects, builders can enhance energy performance, reduce environmental impact, and improve overall building durability.

 


CLICK HERE to learn more about Rothoblaas’ energy-efficient solutions and how they can transform your construction projects

 

The Russia-Ukraine war has had a massive effect on access to a large number of timber products, particularly birch plywood. Whilst it’s true the majority of Birch world stocks come from Siberia, there’s a misconception that, because the UK no longer has access to this particular supply chain, this material is now out-of-reach to most world markets including the UK.

Thankfully, that’s not the case. In fact, there are a wide variety of alternative birch ply suppliers to be found across Europe, producing for the last 100 years to exactly the same standards as Russian counterparts, and at a competitive price point. Whether from Latvia, Estonia, Poland or Finland, there are other suppliers ready to fill the breach. For example, looking at our own portfolio, I immediately think of UPM’s Finnish WISA-Birch range, which is of excellent quality and in regular supply.
However, whilst like-for-like alternatives are available, the shortages caused by the conflict in Eastern Europe has also, unfortunately, seen a rise in lower quality and even imitation products. So, it’s important for builders to remember not all birch ply is manufactured equally and they should tread with caution when approaching non-Russian ply.  Whilst you can be sure that EU-sourced products have undergone the strictest testing and quality control, the same cannot be said for cheap, less credible imports being seen by some as an identical replacement for Russian ply at a lower price. Let’s get this straight now, it’s not, and here’s why.  As readers will know, plywood is a multi-layer product in which the grain of each layer of veneer is alternated crosswise to create a strong surface. In Russia and Europe this is 11-13 plies for 18mm, whereas cheaper Asian imports only incorporate seven. Superficially, you might think you’re buying a better value alternative, but you’re actually purchasing an inferior one, on every level.  Even worse, our dedicated ply team has heard that some producers in Turkey, Kazakhstan and China are using individual laminates of Russian Birch, which are then manufactured into plywood sheets ‘in country’ to make a finished product. This is neither good quality or, for that matter, legal, and should be avoided at all costs.  So, my advice is: if you’re looking for a like-for-like Non-Russian ply, stick with officially certified European replacements to avoid potential disappointment when the cheap substitute doesn’t meet expectations.

That’s not the whole story when it comes to Russian birch ply alternatives. Recent improvements in plywood performance and composition have also resulted in other, similar, sustainable products within the category. These new materials, which use a variety of different timber veneers, offer the same quality as birch ply, creating a broader selection to reduce the impact of supply shortages.  One of these is Garnica’s maple-faced Reinforced plywood, one of the most exciting new ply products available. Created in response to the recent turmoil in the birch ply market, Garnica Reinforced is an industry first. Essentially, it enhances the properties of poplar ply, a softwood, by alternating each layer with a robust blue gum eucalyptus veneer match, competing toe-to-toe with its birch counterpart for strength.  With a slightly pinker face, opposed to the creamier birch, in a long grain format, a look currently popular in the specification market. It offers a near identical alternative at a very similar price point to Russian Birch and Non-Russian Birch.  In most cases, these offer the same, if not better, quality than those products currently out of reach. Furthermore, as with Garnica Reinforced, the scarcity of one material is creating the space for other high-performance timbers to come onto the market.

Going further, this search for alternatives not only applies for decorative ply, but structural materials too. For example, since the Russia-Ukraine conflict began, we’ve also noticed a recent uptick in enquiries for UPM’s WISA-Spruce. This has come predominantly from the off-site community, which is now taking full advantage of the product’s high-strength and relative light weight for structural and load-bearing applications.  As you can see, there’s so much going on, and I’ve only scratched the surface of what’s coming online in terms of timber.  Ultimately, it’s about working with trusted suppliers. Unfortunately, the international situation has also seen a lot of inferior products come onto the market, from questionable sources. So, I’ll finish by reiterating the importance of working with materials partners who can prove their claims and credentials. A best practice operator will have nothing to hide, and ensure you only receive the highest quality materials when searching for a suitable alternatives, especially for Russian birch ply.

Stu Devoil, Group Head of Marketing, James Latham

 


CLICK HERE TO VISIT THE LATHAM TIMBER WEBSITE

Bespoke Fibrelite GRP composite trench covering solution, 82% lighter than cast iron

Once in a while, a product will come along whose performance will drive a change in standards across entire industries. Like stainless steel. Or concrete. Or a trench cover which is over 80% lighter than the cast iron traditionally used, eliminating the need for costly specialised lifting equipment and the accompanying health and safety hazards. And, unlike metal and concrete infill covers, it’s engineered from a GRP composite material which is inert and impervious to corrosion from water and salt, as well as many other corrosive constituents.

 

Changing The Standard For Health & Safety

Heavy metal trench covers come with inherent H&S hazards & often require specialised lifting equipment lightweight Fibrelite GRP trench covers eliminate manual handling risks

Fibrelite’s GRP composite trench and manhole covers are fast usurping metal and concrete covers to become the standard for high-performance industries like airports, commercial ports, leisure cruise terminals, military and defence, power generation (both traditional and renewables), and data centres, with companies like Magnox, The National Grid, all branches of the UK armed forces, and the world’s largest technology brands specifying Fibrelite covers for new build and retrofit projects.

Recent Installation: Port Cruise Terminal Upgrade, UK

As part of this Southern English Port’s cruise terminal upgrade project, Fibrelite was approached by the end-user, who was providing the Onshore Power Supply (OPS) systems. The port had previously considered installing cast iron trench covers to cover the 500 metres of trench housing the high-voltage power cables, but due to their weight (approximately 350 kg) and the additional associated overheads, they approached Fibrelite for a lighter alternative.

Fibrelite developed a bespoke covering solution made up of dozens of custom-sized F900 (90-tonne) load-rated GRP composite trench covers in varying dimensions to suit the specified trench rebate dimensions, which were 65 kg, 82% (285 kg) lighter than the cast iron alternative. The Fibrelite covers are light enough for safe removal with the site dolly, complying with the load rating requirement of the site.

Recent Installation: Major Southern UK Airport Off-Apron Lighting Pit Upgrade

At one of the UK’s busiest airports, Fibrelite designed and manufactured a retrofit replacement for manhole covers over off-apron runway lighting pits where onsite staff have a window of approximately two minutes to effect maintenance and/or repair works between take-offs and landings, including removing and replacing the F900 load rated access cover. The new lightweight GRP composite Fibrelite covers now allow safe, fast access to the lighting pits, maximising time for maintenance and minimising the risk of injury.

 

A Bright Future For Fibrelite

I’ve been a part of the Fibrelite journey since 2011, and it’s been exciting to play a part in driving the upgrade from traditional concrete and metal trench and manhole covers to GRP composites in myriad industries, especially those where manual handling is critical, and seeing how we’ve helped increase health and safety and performance in those industries. We expect to see more and more industries make the upgrade to Fibrelite composite covers, especially in mission-critical areas.

Jo Stott, Marketing Director, Fibrelite


CLICK HERE TO Explore Fibrelite’s technical case study library

 

 


 

Passive fire protection specialist FSi has added the new UK mark of compliance to all its qualifying products more than two years ahead of the deadline – offering customers further assurance of its high standards.

Although the date for compliance has been pushed back to June 2025 for construction products as the UK transitions aways from the European CE scheme, FSi has already secured this for the majority of their range; including their Sealants (Pyrocoustic, Pyrolastic, PyroPro HPE and LST), Stopseal Batts, PipeBloc PCP Collars and PipeBloc PWP Wraps.

From June 2023, the company’s fire stopping products will be labelled bearing the UKCA mark. This follows successful technical assessments by a Government-approved body, following work within FSi to provide the comprehensive documentation and control processes required.

The UK Conformity Assessment (UKCA) mark has been introduced by the Government to show that manufactured products are fit for the market in Great Britain and meet relevant requirements relating to health, safety and the environment.

The CE mark was originally set to be replaced by UKCA on January 1, 2021, which was then pushed back to January 2022. However, for products used in the construction industry, which includes passive fire protection, the date was extended even further until June 30, 2025.

Based in Measham, in Leicestershire, FSi manufactures a range of fire stopping systems that are used in the envelope of a building to limit the spread of a fire. Fire stopping is a process of adequately sealing imperfections in the building, or breaches to walls or floors by penetrations or linear gaps to create a compartment.

Matt Metcalfe, Firestop Manager at FSi, said:

 

“FSi takes responsibility for the quality, safety and performance of its products at every level, and this means showing compliance and backing that up with technical data and proof of performance.

“In adding the UKCA mark of compliance to our products as early as possible we underline that commitment to standards, accountability and taking responsibility for the products that we manufacture.

“Compliance, testing and thorough documentation are second nature to us as a passive fire protection manufacturer and we will always go that extra step to show that we meet requirements, legislation and testing related to our products.

“The technical team worked hard to ensure that all the relevant documentation was in place to support the checks and testing required to achieve compliance.”

“As FSi manufactures products for the global market we understand the need for product confidence, particularly in fire protection products and are happy to have been able to show our compliance.”


CLICK HERE FOR THE FSI WEBSITE

 


 

Modular manufacture of new homes has a track record of delivering big savings. Big savings on time alongside big cost efficiencies. This also extends to carbon reduction.

John Duckworth, Director of Commercial Sales, Deceuninck

 

 

 

A recent study by the University of Cambridge and Edinburgh Napier University found factory-produced homes can lower the carbon footprint of new homes by as much as 45% compared to traditional methods of residential construction.  The study last year of two modular housing schemes in London totalling more than 900 homes, saved a combined 28,000 tonnes of carbon.
“The modular housing sector is making some very exciting inroads into reducing its carbon footprint, with lower energy usage and more efficient manufacture, reducing input costs – but also lessening environmental impact”, says John Duckworth, Director of Commercial Sales, Deceuninck.

 

“As suppliers of energy efficient windows and doors into the modular sector, we’re conscious of the part we have to play in lowering the carbon embodied in new homes and have made a pledge to significantly reduce it.”   Deceuninck committed to ambitious targets to reduce greenhouse emissions through the corporate carbon reduction scheme, Science Based Targets (SBTi) in 2022.

This includes a commitment to cut the CO2  emissions from its own operations (Scope 1&2) by 60% by 2030 from a 2021 baseline. Allowing for future growth in real terms this means reducing CO2 per tonne of product produced by 75%. This goes significantly beyond the SBTi minimum target of 42%.  It has also committed to cut emissions from within its supply chain (Scope 3 emissions) by 48% per tonne by 2030, as part of its wider journey to net-zero greenhouse gas emissions by 2050.

 

“We see it as an opportunity for our customers across sectors”, continues John. “As we lower our scope 1 and two emissions, by default, we lower the scope 3 emissions of our customers, contributing to an overall lowering of the carbon footprint of new build schemes.”

Embodied carbon, which is emitted by the production and transport of materials during a scheme’s construction, currently accounts for around 11% of global emissions.

In the UK, emissions from embodied carbon are between 40 and 50 million tonnes. Emissions are lower in modular builds because of efficiency gains in manufacture but also fewer transport movements to and from site.  As part of its strategy Deceuninck has invested more than €15million in one of the world’s most advanced recycling and compounding facilities to create the capacity to reprocess up to 45,000 tonnes of post-consumer and post-manufacturing PVC-U per year.  In real terms this gives it the capacity to prevent more than three million windows from going to landfill annually.

“The window and door industry is committed to rising to the challenge. Deceuninck developing low carbon manufacturing technologies and a new generation of products which deliver big through-life energy efficiency gains”, John explains.

“We’re designing and developing windows and doors which deliver an enhanced level of performance through-life, but which are easier to recycle and use lower energy to do so, at end of life.”  With Future Homes looming large on the horizon in 2025, the through life performance of windows and doors, is under the microscope, with fundamental changes to window design inevitable.  According to the National Housing Federation the UK’s 29million homes produce 58.5million tonnes of CO2 every year. That’s more than the CO2 produced annually by all car journeys.  It also makes up round 14% of the UK’s emissions and with a commitment to cut total UK emissions by 80% relative to 1990 levels by 2050 under the Climate Change Act (2008), that’s a big problem for Government.  As a key element of the building envelope and a potential major source of CO2 (according to Government figures, 18% of heat loss occurs through windows), windows and doors are a key element of the building fabric.  “This was recognized in the changes to Part L that we saw last year which introduced a new requirement of 1.2W/m2 K for new build windows and doors; and 1.4W/m2 K for replacement windows and doors.
“It was, however, in fact just the start of what will be a series of performance changes for windows and doors in the coming two-to three years, with consultation on future changes to Part L, and under the Future Homes Strategy, imminent”, continues John.
“This could see u-values for new build reduced to as low as 0.8W/m2 K, or more likely 0.9W/m2 K. Even at the latter, the modular housing sector and its supply chains, are going to have to re-think window and door specification because products as they sit today, aren’t going to deliver required performance.”

Deceuninck’s new energy efficient fiberglass composite window system has been developed as a future-proof window system with u-values as low as 0.8W/m2K.   It’s defined by contemporary minimalist features, creating a strong architectural aesthetic which replicates aluminium in an advanced, low maintenance and energy efficient, composite system.  John continues:

“Elegant, our award winning, new ultra-energy-efficient window and door offer sits within our wider sustainability strategy.  “It’s a next generation window system which has been designed to deliver exceptional through life performance, while it’s also easier and use less energy to recycle at end-of-life”, he explains.  “Factory-built homes have been proven to lower carbon-footprint.  “Partnerships with building products suppliers who are pursing innovative programmes to do the same within their businesses, can support the modular sector in delivering even bigger savings by lowering embodied carbon in manufacture and delivering better performance, through life.”


For more information about Deceuninck’s product and service offer please

 

call 01249 816 969

 

email deceuninck.ltd@deceuninck.com

 

OR CLICK HERE TO VISIT THE WEBSITE

 

 


 

Hamworthy Heating helps charity to lower operational costs and reduce carbon footprint

 

When Hull and East Yorkshire Centre for the Deaf needed a modern heating system to replace its existing boiler which was experiencing faults, Hamworthy Heating stepped in to provide the charity with the Stratton mk3 wall-hung condensing boiler, free of charge, to help the charity to achieve maximum savings.

To evaluate the heating requirements of Hull & East Yorkshire Centre for the Deaf, a site visit was commissioned free of charge by Tucker Mechanical and Electrical Building Services. With cost being a major consideration for the charity, Tucker Mechanical and Electrical Building Services decided that the Stratton mk3 wall-hung condensing boiler system with stainless steel heat exchanger would be was the best way forward, both for costs and carbon footprint reduction. in helping the charity reduce its carbon footprint and lower operational costs.

The selected model delivers an output of 70kW, a gross seasonal efficiency of 95.5% and features an integral sequence controller, 5:1 turndown and quiet operation. Accessories also supplied include two frame and header kits to increase the overall output of the boiler system up to 140kW, a plate heat exchanger, pressurisation unit and an expansion vessel.

Moving to the Stratton mk3 wall-hung system provides the building with a space-saving alternative to its previous floor-standing unit. Featuring a lightweight stainless-steel design and a compact footprint, the Stratton mk3 was installed on an internal frame. This allowed space to fit pump equipment and a plate heat exchanger for hydraulic separation to preserve the internal boiler components.

Tucker Mechanical and Electrical Building Services (formerly known as Neville Heating Ltd) has over 40 years of growth and experience in the mechanical and electrical services sector. Based in Hull, the company has a long and well-established relationship with Hamworthy Heating.

 

“As a company, we only align ourselves with reputable companies which offer quality products and Hamworthy has never let us down. Always on hand to provide valuable support and advice, the Hamworthy team is reliable, efficient and always a pleasure to work with”, comments Kevin Peacock, Tucker Mechanical and Electrical Building Services.

 

Following the upgrade, Hull and East Yorkshire Centre for the Deaf now benefits from a reliable and energy-efficient stainless steel boiler system which has enabled the charity to reduce its carbon footprint, lower fuel bills and achieve future maintenance and servicing savings.


CLICK HERE for more information on the Stratton mk3 wall-hung condensing boiler

and range of AHRI certified® plate heat exchangers

  

OR call 01202 662 552

 


.

Modular construction pioneer Wernick Buildings recently completed a new healthcare clinic located in Greater London.

Due to the closure of the previous three-story Roehampton building on site, Kingston Hospital NHS Foundation Trust was looking for a new purpose-built unit to house its growing outpatient services for the Gynaecology, Audiology and Ear, Nose and Throat departments.

After a discussion with the Wernick Buildings team, it was decided that two separate modular healthcare buildings onsite would offer the most timely and cost-effective solution to accommodate all three hospital departments.
The first building delivered by Wernick was the Gynaecology Outpatient Clinic (Willow Building.)  Through a competitive tender process, Wernick Buildings presented a full turnkey solution, which included a complete groundworks package and service connection.

Designed for outpatient use, the two-storey BREEAM-rated block offers several HTN/HBN-compliant amenities including consultation areas, procedure and recovery rooms, staff offices, changing facilities and accessible toilets. The reception and waiting area feature an open floor plan, creating a spacious welcome area for patients.

The building is comprised of 30 modules and showcases sleek cladding, PV panels, and a state-of-the-art plant room on the second storey.

Wernick worked closely with ADP Architecture during the design process. Clinic nurses, doctors and other staff were also consulted in the planning process, assuring their specific needs and requests were met.
Clinical Director Meena Shankar remarked on the speed and usefulness of the new clinic.

“The building was ready to use very quickly and is very modern and comfortable,” said Meena. “We were excited about being involved with the design team from the beginning to get exactly what we wanted.”

The clinic features a modern interior with a cool green colour pallet. Its interior was designed to help provide a calming environment for patients who may be undergoing difficult procedures. The layout boasts a convenient one-way traffic system to support improved infection control measures highlighted through COVID and includes a patient-sensitive discrete exit.

Wernick was also able to provide two temporary modular office buildings to house other displaced departments immediately following the closure of Roehampton Wing.

The building modules were constructed off-site, which allowed for minimal disruption and noise pollution to the surrounding area.

Crews overcame several challenges when transporting and installing the modules into place on the property. The building site was landlocked by three roads and located at the front of the hospital entrance near an Ambulance & Emergency facility. Crane operatives had to take special care to manoeuvre the modules in a dense area surrounded by other buildings.

A second clinic (Aspen Building) housing the Audiology and Ear, Nose and Throat departments was completed in Spring 2023.

Wernick Buildings has decades of experience in delivering modular solutions in the healthcare sector and is highly skilled at working around live clinical building settings. Design, manufacture and site teams are located in-house, providing you with a single point of contact for peace of mind throughout the project. Wernick’s flexible modular systems provide cost efficiency, shorter and more reliable programmes, and improved quality and sustainability.
Offsite construction methods are attractive to NHS trusts as they can dramatically reduce build programmes. Facilities can be operational in a matter of months, compared to years for many traditional build projects. They also reduce onsite disruption and associated health and safety risks.

The Wernick building system is designed to deliver compliant hospital wards and clinical spaces via standardisation with compliancy requirements being applied to building systems. This streamlines the construction process by incorporating pre-approved designs.

Aside from integrating standard NHS specifications, modular construction can offer clients the option to create bespoke building designs tailored to their specific requirements.

 


www.wernick.co.uk


 

UK, June 2023 – TRILUX, a renowned leader in lighting solutions, has successfully partnered with the HC Miraflores Hospital in Zaragoza, bringing together aesthetics and functionality to create an exceptional lighting environment. The HC Miraflores Hospital was recently honoured with the prestigious Ricardo Magdalena Architecture Trophy, recognising its architectural excellence.

Healthcare facilities face unique challenges in meeting the stringent requirements necessary to ensure the well-being of patients and healthcare personnel. Among these challenges, lighting stands out as a crucial aspect in designing and constructing a new health complex. Lighting must be tailored to the specificities of each environment and the diverse activities within the facility.

Recognising the importance of lighting in healthcare environments, TRILUX provided the ideal solution for the lighting needs of HC Miraflores Hospital. with an extensive portfolio, remarkable adaptability, and efficient production centres, TRILUX rose to the challenge of illuminating this state-of-the-art medical facility.

TRILUX’s partnership with the Hernán Cortés Hospitals Group was instrumental in meeting the unique project requirements. The Group sought a reliable and innovative partner capable of delivering agile and adaptable lighting solutions to support their modern and technologically advanced facilities. With fewer luminaire references, TRILUX ensured aesthetic and technical uniformity throughout the hospital, covering all areas except for the operating rooms and reception.

Within the healthcare environment, lighting serves a dual purpose of functionality and ambience. In examination rooms, creating a calming and pleasant atmosphere for patients is essential, while treatment areas demand optimal lighting conditions for accurate diagnosis and medical procedures.

TRILUX addressed these diverse needs by installing their AMATRIS and SIELLA luminaires. In corridors and waiting rooms, AMATRIS luminaires provided a flexible and quick-installation solution, offering decorative potential and influencing the premises’ ambience through design and lighting effects. Incorporating SIELLA luminaires added an austere style and pleasant light, seamlessly integrating into any space.

TRILUX also introduced the OLEVEON FIT luminaire, featuring innovative 3D prism technology for homogeneous and glare-free lighting. This solution significantly reduced energy consumption while delivering exceptional light quality by leveraging modern LED technology.

TRILUX’s expertise in lighting solutions for healthcare facilities ensured the implementation of a future-proof lighting solution at HC Miraflores Hospital. By offering tailored lighting solutions to meet the specific needs of different areas within the hospital, TRILUX demonstrated its commitment to providing efficient and effective lighting solutions.

Discover how TRILUX’s expertise and know-how in healthcare lighting can support your facility with an optimal lighting solution. Enhance the well-being of patients and healthcare personnel while achieving a harmonious blend of aesthetics and functionality.

 


FIND OUT MORE – CLICK HERE

 


 

 

GEZE has launched Revo.PRIME a new premium solution for revolving doors. The new operator boasts an exceptionally low canopy height, narrow profile systems and an improved running performance.

Providing maximum transparency the Revo.PRIME is perfect for creating beautiful entrances and is especially suited for hotels and offices or any building where a statement entrance is required. With its class leading canopy height of just 75mm which houses the automation it ensures the minimal aesthetic whilst achieving excellent technical functionality. In addition the narrow profiles of just 60mm on the door leaf and side panel create a visually appealing entrance and increased transparency creating a light and airy entrance.

 

The Revo.PRIME is environmentally friendly as well, the operator saves up to 30 per cent in energy compared with its predecessor models which is achieved through the drive unit’s reduced power consumption.

Another benefit of the Revo.PRIME is its improved running performance. The brushless direct current motor (BLDC) with 1,000 Nm torque and the enlarged diameter of the door system, up to 3,800mm, ensures ease of access and meets the demands of today’s architects and designers.

 

 

Available in 3 or 4 leaf versions and in a choice of gold, silver and black the Revo.PRIME can be networked to building automation systems via BACnet.

Andy Howland, Sales and Marketing Director of GEZE UK, said

“The Revo.PRIME is an impressive edition to our range of automatic operators and one that is sure to delight architects and specifiers giving them the freedom to design stunning entrances.”


To find out more about the Revo.PRIME visit the CLICK HERE

see it in action on

YouTube

 

or email

info.uk@geze.com

 

CLICK HERE

for more information about GEZE UK’s comprehensive range

of automatic and manual door closers